PSU wise Common Carrier Natural Gas pipeline networks (Operational, Partially Commissioned and Under Construction)
This dataset contains name of the company-wise length and capacity of operational, partly commissioned and under construction natural gas pipeline network in India
Note:
1. MMSCMD stands for Million Metric Standard Cubic Meters per Day
2. Total authorized Natural Gas pipeline length including Tie-in connectivity, dedicated & STPL is 34,233 kms (P),however total operational pipeline length including Tie-in connectivity, dedicated & STPL is 25,429 kms (P) and Under Construction Pipeline length including Tie-in connectivity, dedicated & STPL is 10,459 kms (P)
PSU wise Common Carrier Natural Gas pipeline networks (Operational, Partially Commissioned and Under Construction)
This dataset contains name of the company-wise length and capacity of operational, partly commissioned and under construction natural gas pipeline network in India
Note:
1. MMSCMD stands for Million Metric Standard Cubic Meters per Day
2. Total authorized Natural Gas pipeline length including Tie-in connectivity, dedicated & STPL is 34,233 kms (P),however total operational pipeline length including Tie-in connectivity, dedicated & STPL is 25,429 kms (P) and Under Construction Pipeline length including Tie-in connectivity, dedicated & STPL is 10,459 kms (P)
Rows: 1152
Columns: 7
Time period: 2022 to 2025
Last Updated: 07 September 2026
Data preview
as_on_date
nature_of_pipeline
value_type
entity
value
unit
note
31-03-2026
Total length
Length
RGPL
304
value in Kilometers
31-03-2026
Operational
Capacity
IOCL
25.23
value in Million Metric Standard Cubic Meter per day
31-03-2026
Partially commissioned
Length
IOCL
1121
value in Kilometers
31-03-2026
Total operational length
Length
IOCL
1370
value in Kilometers
31-03-2026
Under construction
Length
IOCL
806
value in Kilometers
31-03-2026
Under construction
Capacity
IOCL
7.87
value in Million Metric Standard Cubic Meter per day
31-03-2026
Total length
Length
IOCL
2176
value in Kilometers
31-03-2026
Operational
Length
AGCL
107
value in Kilometers
31-03-2026
Operational
Capacity
AGCL
2.42
value in Million Metric Standard Cubic Meter per day
Petroleum Planning and Analysis Cell. (2026). PSU wise Common Carrier Natural Gas pipeline networks (Operational, Partially Commissioned and Under Construction) [Data set]. Dataful. https://dataful.in/datasets/17466